link ae888

HCM City drainage not yet ready for heavy rain

Flooding in HCM City in the coming rainy season is expected to be more severe because most drainage projects have not been completed, project managers say.
Flooding in HCM City in the comingrainy season is expected to be more severe because most drainageprojects have not been completed, project managers say.

The city has four big ongoing drainage projects, the Nhieu Loc-ThiNghe Basin 's environment clean-up project, the East-West Highwayand Water Environment project, the city's urban enhancement projectand Hang Bang Canal project.

Phan Hoang Dieu, director of the Nhieu Loc-Thi Nghe Project'smanagement board, said new culverts have been installed under moststreets, but would not be connected to the city's common drainage systemuntil 2011.

Installation work during the last phase of the East-West Highwayand Water Environment project is expected to be completed next year.

"Even though many culverts have been installed upstream for theseprojects, there is still work to be done with the outlets, so theupstream culverts aren't effective at this time," Dang Ngoc Hoi, sectionhead of the project's management board, told Lao Dong (Labour)newspaper.

The Hang Bang Canal Project, which is expected to deal with floodingin districts 6, 11, Tan Binh, Tan Phu and Binh Tan, is still in itsfirst phase. The city's Steering Centre for Anti-flooding Programme saidthe city's drainage system in more than 100 areas has been blocked byconstruction work of the Nhieu Loc-Thi Nghe Project and WaterEnvironment project.

The projects have stopped water flow to complete work. If these areasare not unblocked the centre warned that many areas in the city's innerdistrict 1 would flood during the rainy season./.

See more

The Prime Minister’s Certificates of merit are awarded to two units and two individuals for outstanding contributions to the nationwide campaign “Joining hands to eliminate makeshift houses in 2025.” (Photo: VNA)

Thai Binh completes housing upgrade programme 🍌ahead of schedule

At a review conference held on June 21, Deputy Minister of Construction Nguyen Van Sinh praised the province’s scientific, coordinated, and flexible approach. He noted that the early completion reflects the strong commitment of local authorities, the business community, philanthropists, and residents in improving housing conditions for disadvantaged groups.
The VNA launches its multimedia information portal on June 20. (Photo: VNA)

Vietnam News Agency launches mult꧟imedia platform

The strategic product, managed and operated by the Vietnam News Agency Digital Media Centre (VNA Media), is an official channel for popularising the Party and State’s information and documents as well as delivering mainstream and trustworthy news to both domestic and international audiences through various kinds of multimedia formats.
{dagathomo tructiep hôm nay}|{link link link ae888}|{dá gà thomo}|{trực tiếp đá gà thomo hom nay}|{sbobet asian handicap}|