link ae888

Progress, investment disbursement of North-South Expressway sub-projects accelerated

Contractors of the eastern North-South Expressway sub-project are actively pooling machinery and manpower to accelerate its construction progress in line with the commitments made to the Ministry of Transport (MoT).
Progress, investment disbursement of North-South Expressway sub-projects accelerated ảnh 1The contractor is responsible for laying asphalt in a section of the eastern North-South expressway project in the 2017-2020 period. (Photo: VietnamPlus)

Hanoi (VNA)🤡 – Contractors of the eastern North-South Expressway sub-project are actively pooling machinery and manpower to accelerate its construction progress in line with the commitments made to the Ministry of Transport (MoT).

A series of North-South expressway sub-projects are being pushed by the MoT to accelerate disbursement and meet the schedule. For contracts that are progressing slowly, the Project Management Unit No 2 transferred the workload to other contractors to assist in speeding up construction. It also requested the deployment of additional machinery and asphalt to ensure timely construction for sections where the conditions are suitable for load removal in areas with weak grounds. As the contractor that nearly completed the XL2 package of the National Highway 45-Nghi Son Expressway sub-project, Nguyen Manh Tuan, director of the XL2 package management board under Lizen Company, said since July 27, the consortium of Lizen and 471 JSC has taken over the entire construction of the asphalt concrete overlay for a 7.6km stretch from the XL3 package.
It is expected that by August 25, the entire task of Lizen and other supporting contractors will be completed, he added. Regarding My Thuan 2 bridge project, a component project of the North-South expressway project in the 2017-2020 period, the project management unit's report indicated that the completed construction output has reached 87% of the contract value. The entire project is set to be completed by the end of this year. After over seven months of construction, there has been a noticeable improvement in the construction progress and resource mobilisation for Hau Giang-Ca Mau section of the North-South expressway project. According to a report from the My Thuan project management unit, the construction output has reached nearly 800 billion VND, which is approximately 7% of the contract value and about 60% of the registered contractor's plan.
Progress, investment disbursement of North-South Expressway sub-projects accelerated ảnh 2The contractors are taking advantage of favourable weather conditions to expedite construction progress and disbursement. (Photo: VietnamPlus)
  This year saw completion and operation of three North-South expressway subprojects, including National Highway 45-Nghi Son, Nghi Son-Dien Chau, My Thuan 2 Bridge, and My Thuan-Can Tho project. The MoT has been directing contractors to pool all possible resources, capitalise on favourable weather conditions, and arrange "3 shifts, 4 teams" to ensure the projects are put into operation on schedule and to avoid delays.
Progress, investment disbursement of North-South Expressway sub-projects accelerated ảnh 3The supply of sand materials and land base remains a challenge in several North-South expressway sub-projects. (Photo: VietnamPlus)
The MoT also requested investors and relevant agencies to urge contractors to pool all possible resources, take advantage of favourable weather conditions, and continue with construction to meet schedule and disbursement plans. It called for attention to quality management, labour safety and fines against underperforming contractors and those violating contract schedules in accordance with regulations. Recognising the prerequisites and the biggest obstacles to the completion of the eastern North-South expressway project for the 2021-2025 period, the MoT directed contractors to work with localities to expedite the completion of procedures for exploiting construction material quarries.
The hope is a completion date of the end of July and early August 2023 for quarries that have been submitted. Additional quarries that meet criteria for quantity, quality, and procedural convenience regarding land should be surveyed and included in the material survey file for the project (if needed) and complete procedures for remaining quarries no later than October 2023./.
VNA

See more

A motorbike production line of Honda Vietnam — a Japanese company located in Phu Tho province. (Photo: VNA)

𒉰 Phu Tho emerges as FDI magnet following mergence

In the first seven months of the year, Phu Tho attracted an impressive 651.7 million USD in foreign direct investment, including 35 newly licensed projects totaling 119 million USD in registered capital and 45 existing projects with an additional capital of 533 million USD.
Infraction levels will correspond to fines of 1-80 million VND, depending on the nature and number of invoicing violations. (Photo: vietnamfinance.vn)

𝔉 Maximum fine of 3,000 USD proposed for violating invoice regulations

Under a draft to amend and supplement the Government's Decree 125/2020/ND-CP on administrative sanctions for violations of tax and invoice regulations, the Ministry of Finance has proposed classifying the failure to issue invoices into five different levels. Infraction levels will correspond to fines of 1 million VND to 80 million VND, depending on the nature and number of invoicing violations.
At the strategic partnership signing ceremony between Sun PhuQuoc Airways and Amadeus. (Photo: Sun Group)

🎐 Sun PhuQuoc Airways enters strategic partnership with Amadeus to build a five-star aviation technology ecosystem

A new airline developed and invested by Sun Group — has officially announced a strategic partnership with Amadeus IT Group (Amadeus), one of the world’s leading travel technology companies. This agreement not only lays the foundation for a modern digital infrastructure but also marks a pivotal step in SPA’s global expansion strategy, enabling the airline to access international distribution networks and reach customers worldwide.
A local resident makes a bank transfer using the Momo app. (Photo: VNA)

𝓀 Banks accelerate digitalisation, non-cash payments

Cashless payments are growing at an impressive rate, averaging 30–40% annually. Vietnam’s per capita cashless transaction volume now trails only China, with total value of 295.2 quadrillion VND (11.26 trillion USD), or 26 times of its GDP.
{dagathomo tructiep hôm nay}|{link ae888 city 165}|{dá gà thomo}|{trực tiếp đá gà thomo hom nay}|{sbobet asian handicap}|